Asia Law Network Blog

Hong Kong: The Competition Tribunal refuses last-minute application to amend pleadings two months before trial

Reading Time: 4 minutes

Introduction

In Competition Commission v Wing Hing Construction Co Ltd [2018] HKCT 6, the Competition Tribunal refuses a respondent’s application to amend its Response and file new witness statements in substitution for a statement already filed.

Factual background

In these proceedings, the respondents were contractors appointed from a reference list of the Hong Kong Housing Authority to perform decoration work for tenants of public housing units in three buildings in On Tat Estate in Kwun Tong. The applicant, the Competition Commission (the “Commission”), alleges, among other things, that between June and November 2016, the respondents made or gave effect to an agreement or engaged in a concerted practice among themselves to allocate various floors of each of the three buildings among themselves to carry out decoration work. It is also alleged that the respondents made or gave effect to an agreement or engaged in a concerted practice whereby they jointly produced promotional flyers setting out package prices.

The Commission argued that the above arrangements (1) contravened the first conduct rule in the Competition Ordinance (Cap. 619) (the “Ordinance”), and (2) amounted to serious anti-competitive conduct in the form of market sharing and price-fixing. The Commission seeks a declaration accordingly and an order for pecuniary penalty against the respondents. The fourth respondent is a partnership named Tai Dou Building Contractor (“Tai Dou”).

Relevant course of proceedings

The action was brought in the Competition Tribunal by the Commission’s Originating Notice of Application on 14 August 2017. The solicitors for Tai Dou filed a Notice to Act and Response on 28 September 2017. On 23 October 2017, the first Case Management Conference (CMC) was held at which various directions were given for the further conduct of the proceedings including a direction that the trial be targeted to take place during the period of 12 November to 14 December 2018. Subsequently, Tai Dou filed a witness statement made by Mr KC Ho, its General Manager of Tai Dou, on 19 April 2018 (“1st witness statement”). Between June and September 2018, Tai Dou had changed its legal representatives for two times.

Tai Dou made the present application on 24 September 2018, on the basis that Tai Dou did not authorise Mr KC Ho to undertake any relevant decoration work in relation to On Tat Estate under the name of Tai Dou, and Mr KC Ho had bored all the costs and retained all the revenues and profits arising from any decoration work performed. In essence, Tai Dou sought to completely overturn what was pleaded in the 1st witness statement and argued that its partners were kept completely in the dark of Tai Dou’s involvement in the proceedings.

When the present application was filed, the Commission and all other respondents were ready to proceed with the trial which would commence on 26 November 2018.

Decision

The Tribunal considered Tai Dou’s application to be made at a very late stage when other parties were under a tight schedule in preparation for the trial which had been anticipated to take place for over one year. While delay on its own may not be sufficient to justify a refusal of leave to amend pleadings, the application had to be placed in the context of the procedural history of the case and the forthcoming trial dates. In addition, Tai Dou failed to produce sufficient and compelling evidence of communications between its partners and Mr KC Ho in support of its present application. The partners only began to take an interest in the proceedings in around early September 2018 when they learnt that the maximum pecuniary penalty that could be imposed under the Ordinance was referable to the turnover of the undertaking and not just the turnover of the estate project in question.

The Tribunal accepted the Commission’s argument that very substantial factual investigation would have to be carried out to meet Tai Dou’s new case. In particular, it was found that Mr KC Ho had carried out decoration work in the name of Tai Dou in other public housing estates in 2006, 2008, 2010 and 2013 respectively. Even though other respondents had also raised the “sub-contractor” argument, the Commission would require significant amount of time to analyse Tai Dou’s new arguments such that the trial dates would have to be vacated. There was no justification to force the Commission to squeeze its investigation, preparation and decision-making processes all into the coming few weeks especially when it already, through no fault of its own, had to expend utmost effort towards responding to the factual evidence recently filed by other respondents to proceed with the scheduled trial.

The Tribunal concluded that an adjournment of the trial is now considered itself serious prejudice to the parties involved in litigation. While the present proceedings is an enforcement action under the Ordinance that can be differentiated from an ordinary civil litigation, the s.144 of the Ordinance enables the Tribunal to follow “the practice and procedure of the Court of First Instance in the exercise of its civil jurisdiction”. The Competition Tribunal Rules (Cap. 619D) also provides that cases should be dealt with in an efficient and expedient manner. Thus, Tai Dou’s application was refused.

Implications

The judge stated in obiter that there is a public interest to maintain the integrity of the litigation process in the Competition Tribunal. Further, there is a broader public interest in these enforcement actions to see the proceedings being dealt with as expeditiously as is reasonably practicable. The outcome of these proceedings may well serve as guidance to other undertakings and persons in the regulation of their economic conduct.

The reasoning demonstrates that values upheld within enforcement actions correspond with those promoted in civil litigations. Efficiency in resolving legal proceedings without delay is no doubt an important consideration of the Tribunal in ruling last-minute applications in enforcement actions. Parties should therefore take note of milestone dates of the proceedings and avoid delayed applications to the Tribunal.


This article is written by ONC Lawyers and was first published on ONC’s website.

This article does not constitute legal advice or a legal opinion on any matter discussed and, accordingly, it should not be relied upon. It should not be regarded as a comprehensive statement of the law and practice in this area. If you require any advice or information, please speak to practicing lawyer in your jurisdiction. No individual who is a member, partner, shareholder or consultant of, in or to any constituent part of Interstellar Group Pte. Ltd. accepts or assumes responsibility, or has any liability, to any person in respect of this article.

Keep reading related posts